- November 2006
to September 2007 - 48m x 330m FACTORY FOR GULF PACKAGING INDUSTRIES LTD., Jubail, Saudi Arabia
Client: MADA Company
for Industrial and Commercial Investment Consultant: Saudi Consulting and Design Office Participation: Preparation
of reinforcement drawings and bar bending schedules for 900 tons of steel reinforcement for various foundation works - footings,
pedestals, ground beams, columns, beams, slabs & machine foundations.
- August 2006 to March 2007 - YANBU CEMENT
FACTORY EXTENSION KILN 1 & 2, Yanbu, Saudi Arabia
Client:
Yanbu Cement Factory / BHA Group GmbH Participation: Design of foundation for silo and stair tower structure, bag filter
structure, cable bridges, substation building, fan motor and ducts supports; Design of steel structures for cable bridges
and supports; Design of substation building; Supervision of draftsmen in preparing shop drawings; Preparation of quantity
take-off and order of steel materials for the fabrication; Preparation of bar bending schedules & order of reinforcement.
- April 2006 to March 2007- KHAYYAT NEW JEDDAH RED BRICKS FACTORY, Khulais,
Saudi Arabia
Client: El Khayyat Red Bricks Co. Participation: Design of various foundations for Crusher Plant including
Sieve Structure, Load Hopper Structure, Stair Tower and other steel structures; Preparation of shop drawings
for above-described structures, platforms and ducting works; Preparation of material lists & quantity take-offs
for ordering of raw materials & invoicing purposes; Preparation of bar bending schedules and order of steel reinforcement.
- February 2006 to September
2006 - NON-WOVEN FACTORY, Jubail, Saudi Arabia
Client: MADA Participation: Checking of design drawings
and preparation of all shop drawings for issuance to site; Preparation of bar bending schedules and order of reinforcement
for foundation works, retaining walls, silo foundation, concrete columns, suspended slabs and beams, stairs, ramps and equipment
foundations; Preparation of fabrication drawings of all embedded items like anchor bolts, protection angles, base channels,
gratings, manhole covers etc.
- May 2005 to November 2005 - MPC PAMPERS FACTORY LINE 15
EXTENSION WORKS, Jeddah, Saudi Arabia
Client: Modern Products Co. (Procter & Gamble) Participation: Preparation
of all shop drawings for FAS Building & Production Building including PAROC wall, conveyor platforms, pipe racks,
jib cranes, catwalks, process pipe supports, ladders, bollards and other steel fabrication works; Design for the strengthening
and modification of existing structure to accomodate new line 16 structures; and Quantity take off and order of materials.
- January 2005 to June 2005 - YANBU CEMENT FACTORY EXTENSION (KILN FEED NO.3),
Yanbu, Saudi Arabia
Client: BHA GROUP GmbH Participation: Design of foundation for Stair Tower and Silo Structure,
Bag Filter Structure, Cable Bridges, Substation Building, Fan Motor & Duct Supports; Design of steel structures for Cable
Bridges and Supports; and Preparation of Quantity Take-off and Order of steel materials for the fabrication of Stair Tower,
Bag Filter Structure, Cable Bridges, Substation Building and Duct Supports.
- February 2004 to April 2004 - NFIC EXTENSION WORKS, Jeddah, Saudi Arabia
Client:
National Food Industries Co. Participation: Design and engineering works for new hangar 30m x 7m, order of materials, preparation
of bar bending schedule and site coordination.
- February 2004 - NATEL OFFICE & WAREHOUSE EXTENSION, Jeddah, Saudi Arabia
Client:
National Telecommunications Co. Ltd. Participation: Design of structural steel and foundation for Office and Warehouse
Extension.
- October
2003 to November 2003 - ARABIAN CEMENT FACTORY, Rabigh, Saudi Arabia
Client: KHD Humboldt Wedag AG Participation:
Site supervision for Silo Roof Reconstruction and Strengthening Works at Clinker Silo 5, Cement Silos 6, 7 & 8 and Raw
Mill Silos 7 & 8.
- May 2003 to December 2003 - ENTERPRISE PROJECT - MPC/88, Jeddah, Saudi Arabia
Client:
Modern Products Co. (Procter & Gamble) Participation: Detailed engineering for Workshop & Training Center.
- October 2002 to November 2003 - RED BRICKS FACTORY NO.10, Jizan, Saudi
Arabia
Client: El-Khayyat Red Bricks Mfg. Co. Participation: Design and engineering for the fabrication of
Factory Shed 233m x 38m x 12m high and numerous platforms; Preparation of bar bending schedule and order of materials
for foundation works.
- June 2002 to March 2003 - SAUDI CARTON FACTORY/ UNITED CARTON IND.
CO., Jeddah, Saudi Arabia
Client: Omar Kaseem Alesayi Marketing Co. Participation: Design and engineering for
the fabrication of structural steel for bridge connecting two buildings, 40m high advertisement tower, steel platforms and
other structures.
- June 2002 to January 21, 2003 - EL-KHAYYAT RED BRICKS FACTORY, Bahrah,
Saudi Arabia
Client: El-Khayyat Red Bricks Mfg. Co. Participation: Design and engineering for the fabrication
of structural steel for sheds, supports, platforms, ducts, thermal rooms and other structures.
- May 2002 - BULGHAH GOLD MINE PROJECT, Bulghah, Saudi Arabia
Client:
GCC Olayan Participation: Design of Transformer Foundation.
- May 2002 - ARABIAN CEMENT FACTORY, Rabigh, Saudi Arabia
Client:
Arabian Cement Co. Participation: Design of Roller Support for 65-ton gearbox.
- September to October 2001 - CRISTAL PIGMENT PLANT, Yanbu, Saudi Arabia
Client:
Cristal Co. Ltd. Participation: Detailed engineering and fabrication of Pressure Filter Building.
- June 2001 - YANBU CEMENT FACTORY, Yanbu, Saudi Arabia
Client:
KHD Participation: Design of steel pipe supports including foundation.
- May 2001
- GULF STATIONERY FOR FILE MFG., Industrial City, Jeddah, Saudi Arabia
Client: Gulf Packaging System Co. Participation:
Design of factory 80m x 39m.
- April 2001 - MATTEX FACTORY, Industrial City, Jeddah, Saudi Arabia
Client:
Saudi Co. for Carpet Materials Participation: Design of steel pipe supports, stairs, loading platform and septic tank.
- February to October 2001 - ENTERPRISE PROJECT - MPC/88, Jeddah, Saudi Arabia
Client:
Modern Products Co. Participation: Detailed engineering for the fabrication and erection of structural steel for engineering
workshop, production building, facility building, warehouse link building, production link building and parking shed.
- October 2000 - SAUDI CRYSTAL BUILDING, Yanbu, Saudi Arabia
Client:
Saudi Crystal Participation: Design of four-storey steel building.
- August 2000 - CARPET FACTORY PLANT 1, Industrial City, Jeddah, Saudi Arabia
Client:
Sh. Sorayai Participation: Detailed design of Mezzanine Floor, 44m x 22.5m x 3.8m high.
- July 2000
- MEDICAL PVC FACTORY, Industrial City, Jeddah, Saudi Arabia
Client: TIB Plastic Industries Participation:
Detailed design of V-shaped car shed, 6m wide x 40m long, with 180x8 sq.tube rafter and 5"sch.40 pipe supports.
- June to July 2000 - CARPET FACTORY PLANT 1, Industrial City, Jeddah, Saudi
Arabia
Client: Sheik Sorayai Participation: Design of 3 heavy steel frames to replace 18 existing columns interfering
with new equipment layout. These frames support 9 rafters spanning 45m. Affected area is 45m x 65m.
- May 2000 - AGM PLASTIC FACTORY, Industrial City, Jeddah, KSA
Client:
AGM Participation: Design of 540sqm additional office area over an existing roof. New columns and beams are provided to
carry the loads.
- December 1999 to May 2001- SAUDI MODERN FOOD FACTORY, Industrial City, Jeddah,
KSA
Client: Basamah Trading Participation: Design of foundation for 5000sqm factory, two-storey 450sqm office
building, 576sqm mezzanine floor, pump rooms for firefighting and potable water, and underground tanks for firefighting water,
potable water, untreated raw water, treated raw water and returned water.
- September 1999 - YANBU CEMENT FACTORY, Yanbu, Saudi Arabia
Client:
KHD-Yanbu Cement Factory Participation: Detailed design of Tripper Car Docking Tower, 4.2m x 6m x 17m high.
- October to December 1998 - CARPET FACTORY PLANT 1, Industrial City, Jeddah,
Saudi Arabia
Client: Sheik Sorayai Participation: Design of heavy steel frame to replace existing columns interfering
with new equipment layout.
- July to December 1998 - ATTIEH STEEL FACTORY, Jeddah, Saudi Arabia
Client:
Arabian International Co. Participation: Design of shearing machine foundation, chimney foundation and septic tanks.
- July 1998
- AL-TAYAR PLASTIC & RUBBER FACTORY, Jeddah, Saudi Arabia
Client: Gulf Co. for Packaging Systems Participation:
Design of Building Shed for silos 4.5m wide x 45m long x 8.7m high.
- June to
July 1998 - AL-SALAMA HOSPITAL, Jeddah, Saudi Arabia
Client: Saudi Bauer Participation: Order of materials,
fabrication and delivery of reinforcement for concrete piles of various sizes - dia.450x8m to 12m.
- January to July 1998 - CARPET FACTORY PLANT 2 EXTENSION, Industrial City,
Jeddah, KSA
Client: Sheik Sorayai Participation: Design of foundation and structure for 8 silos, and machine
platform structure, 60 tons total weight.
- January to March 1998 - SAUDI MODERN FOOD FACTORY, Industrial City, Jeddah,
KSA
Client: Basamah Trading Participation: Design of maintenance platform at Boiler Room, platform for pump
and gas tanks, cantilever maintenance platform at silo area and chimney pipes.
- December 1997 - FILM BLOWING LINE TOWER, Industrial City, Jeddah, Saudi Arabia
Client:
Al-Tayar Plastic & Rubber Factory Participation: Design, fabrication and erection.
- November 1997 - LOADING DOCK FOR CARPET FACTORY, Industrial City, Jeddah,
Saudi Arabia
Client: Sorayai Carpet Factory Participation: Design of loading dock between Plants 1 & 3.
Precast cantilever walls were used to avoid interference with the plant operation.
- October 1997 - ATTIEH STEEL FACTORY, Bahrah, Saudi Arabia
Client:
Arabian International Co. Participation: Design of various machine foundations and underground tanks.
- September 1997 - STEEL VEHICLE RAMP, AAA, Jeddah, Saudi Arabia
Client:
Arabian Auto Agency Participation: Structural design of steel modular ramp, 17m long x 6m wide and 1.8m high.
- November 1996 - AL-TAYAR PLASTIC FACTORY, Industrial City, Jeddah, Saudi
Arabia
Client: Al-Tayar Plastic Manufacturing Co. Participation: Structural design of Cantilever Parking Shed.
- December
1995 to August 1997 - SUGAR REFINERY PROJECT, Jeddah, Saudi Arabia
Client: TPL Arabia Ltd. Participation: Overall
Project Engineer. Detailed design and supervision for the preparation of shop drawings, submittals, fabrication, erection
and site works for steel conveyors, towers, supports, bridges, pipe racks, shelters,
handrails, ladders, stairs, gratings, catwalks and other miscellaneous structures.
- August 1995 to January 1998- SAUDI GLASS FACTORY, Industrial City, Jeddah,
Saudi Arabia
Client: Saudi Glass Co. Participation: Design of structures including Switchgear Room supported
by one row of columns, cantilever floor beams and strip footings, Watchman Tower, Retaining Wall for wet sand, Machine Platforms,
Factory Extension and miscellaneous structures.
- October to November 1994 - REFRIGERATED PLANT, WAREHOUSE, OFFICE & ACCOMODATION
BLDG, Halaga, Jeddah, Saudi Arabia
Client: Al-Ghamdi Participation: Structural design of foundation and structures.
- August 1994 - YANBU CEMENT FACTORY, Yanbu, Saudi Arabia
Client:
KHD - Yanbu Cement Factory Participation: Structural design and coordination for the order, fabrication and delivery of
materials for cantilever carport and butterfly carport.
- July 1994 - GSM OVERLAY NETWORK, Jeddah, Saudi Arabia
Client:
Siemens Participation: Structural design of various steel substructures for antennae.
- February
1994 - SAUDI MODERN FOOD FACTORY, Industrial City, Jeddah, Saudi Arabia
Client: Saudi Modern Food Factory Participation:
Structural design, preparation of fabrication drawings, order of materials and overall coordination for Two-Level Maintenance
Platform.
- January to November 1994 - SORAYAI CARPET FACTORY - HARAJ, Jeddah, Saudi
Arabia
Client: Sheik Sorayai Participation: Structural design, preparation of fabrication drawings, order of
materials and overall coordination for the construction of 1 Warehouse with Mezzanine Floor (44mx72mx9m high) and 1 Two-Storey
Showroom (20mx30mx8m high).
- November 1993 - AGM FACTORY, Industrial City, Jeddah, Saudi Arabia
Client:
AGM Factory Participation: Structural design of Additional Room Inside Factory.
- October 1993 - SAUDI MODERN FOOD FACTORY, Industrial City, Jeddah, Saudi
Arabia
Client: Saudi Modern Food Factory Participation: Structural design of Maintenance Platform around silos.
- June 1993
- RABIGH MINING FACTORY, Rabigh, Saudi Arabia
Client: Rabigh Mining Factory Participation: Structural design
of foundation for various machineries and equipments.
- September 1991 - RUBBER FACTORY WAREHOUSE, Gaya-Gaya, San Jose del Monte,
Bulacan, Philippines
Client: Mr. & Mrs. Kameo Nakano Participation: Complete design, drafting, estimate
and supervision.
- April 1991 - BUILDING FOR RUBBER FACTORY, Sta. Maria, Bulacan,
Philippines
Client: Mr. & Mrs. Kameo Nakano Participation: Complete design, drafting and estimate.
- December 1990 - STEEL WAREHOUSE, Bagbag,
Novaliches, Quezon City, Philippines
Client: Mr. & Mrs. Kameo Nakano Participation: Complete design, drafting
and estimate.
|
 |
|
 |
|
 |
|
|
Mailing Address: P.O. Box 6650 Doha, Qatar E-mail address: ronaldnilo@yahoo.com Mobile No.